Jackrabbit Avenue and 7th Street Reconstruction

Road Reconstruction

Project Update

Bowes Construction plans to start on this portion of the project around the first week of July. 

Route/Detour Information

During the majority of the work, Jackrabbit Avenue from 6th Street to 8th Street will be closed to all traffic. 

Project Milestones


STATUS:         Project  Milestone Status CompletedCompleted       Project Milestone Status Not Completed Not Completed
Removal and replacement of sidewalk ramps to meet ADA standards at 7th Street and Jackrabbit Avenue. 


Removal of the street surface and existing subgrade. 


Placing of new gravel base course.


Paving the new street surface. 


Project Overview:

Sidewalk ramp upgrades and street reconstruction. 

Completion Date:

August 15th

Contract Amount

$150,000

Contractor Name

Bowes Construction

Contractor Contact Information

Cole Schneider, Project Manager

605-693-3557

City Contact Information

Charlie Richter, City Engineer

605-692-6629