8th Street South & Main Avenue Intersection Reconstruction

IMG_2127Project Update

Bowes has closed this intersection and finished the removal of the existing pavement. Work on the new water main installation has begun.

Route/Detour Information

See the linked map below for detour information during the course of the project. 

8th Street South & Main Avenue Intersection Reconstruction Detour Map

Project Milestones


STATUS:         Project  Milestone Status CompletedCompleted       Project Milestone Status Not Completed Not Completed
 Remove existing pavement within the intersection


Install new water main through the intersection


Backfill and prep the gravel base course


Install new concrete paving through the intersection & patch asphalt


Apply new pavement markings


Open the intersection to traffic!


Project Overview:

This project entails the reconstruction of the street surface in the intersection as well as some sidewalk ramp and traffic signal upgrades. 

Completion Date:

August 19, 2022

Contract Amount

$612,000

Contractor Name

Bowes Construction

Contractor Contact Information

Cole Schneider, Project Manager

605-693-3557

Consultant Name

Civil Design Inc. (CDI)

Andrew Kangas, PE, LS

(605) 696-3200