7th Street & 12th Avenue Intersection Sidewalk Ramp Upgrades

Ramp 1Project Update

Bowes plans to begin work on this intersection around the middle of September.

Route/Detour Information

Work at 7th Street and 12th Avenue will not warrant a signed detour. East/West traffic on 7th Street will not be affected other than narrowed driving lanes, but North/South traffic will not be able to go through the intersection as it will be closed to install new valley gutters. 

Project Milestones


Phase 1: Ramp Replacements


STATUS:         Project  Milestone Status CompletedCompleted       Project Milestone Status Not Completed Not Completed
Bowes will remove the existing sidewalk, curb and fillets as needed and place the appropriate barricades. 


Clark Drew Construction will install new fillets and curb in the street.


Form and pour the new sidewalk ramps.


Backfill with topsoil and seed.


Project Overview:

This project includes removing and upgrading the existing sidewalk ramps to be ADA compliant. 

Completion Date:

End of October 2022

Contract Amount

$50,000

Contractor Name

Bowes Construction

Contractor Contact Information

Cole Schneider, Project Manager

605-693-3557

City Contact Information

Charlie Richter, City Engineer

605-692-6629